District 1 South Report — February 2021

Here are some District 1 projects:

LAUSD Ascot Ave. ES is a $76 Million school modernization project that will have demolition of existing classroom buildings and new classrooms and administration buildings installed. Baker Electric will do inside electrical and First Fire will perform sound and communications work. The pre-job was at the beginning of January and demolition has commenced. Further information about manpower demand will be coming soon.

An $83 Million dollar Metro Center Street project for Metro Rail Operations and Security Operation is being built at 410 Center St. in Los Angeles. Comet Electric, Advanced Cable Solutions and Global Electric are assigned the work.

Baker Electric is working at a project at White Memorial on Boyle street, and is about to start working two 12-hour shifts to complete a special project for the hospital. They will start to call for manpower very soon.

The Lucas Museum is a SASCO Project that has a lot of steel being installed. They are about to top off the steel and start building larger portions of the project. It is a monumental, $1 billion dollar museum and will be needing a lot of manpower starting in late March.

The HMT Electric high-rise Hotel/Condo is at ground level now at New Hampshire and Wilshire Boulevard in Koreatown. There will be a growing demand for manpower as they pour and build a few levels of the project. April will see a demand for manpower.

Thank you for the Honor to be your District 1 Business Representative.

Shomari Davis
Business Representative